some image

Updates

PUBLIC HEARING : FRIDAY, MAY 15TH, 2015 AT 10:00 AM

Updates

The City of Los Angeles will hold a public hearing to consider and make a recommendation to the Los Angeles City Council regarding  the Final Mitigated Negative Declaration (MND) for this project.

When:
Friday, May 15, 2015
10:00 AM

Where:
Los Angeles City Hall
200 North Spring Street, Room 350
Los Angeles, CA  90012

To learn more about the public hearing,  please refer to the PDF linked below.

Notice of Board of Public Works Hearing

CITIZENS ADVISORY COMMITTEE MEETINGS

Updates

Citizens Advisory Committee Members:

–          Alex Ward, Friends of the LA River (FOLAR)

–          Daniel Chamberlain, Silver Lake/Ivanhoe Parent

–          Deborah Murphy, LA Walks

–          Don Seligman, Los Feliz Improvement Association (LFIA)

–          Don Ward, Los Feliz Neighborhood Council

–          Eric Bruins, Los Angeles County Bicycle Coalition (LACBC)

–          Netty Carr, Atwater Village/Historical Perspective

–          Matthew Mooney, Silver Lake Neighborhood Council

–          Sergio Lambarri, Atwater Village Neighborhood Council

 

The  Citizens Advisory Committee  meetings  which have been held:

1. Thursday, December 12 , 2013

2. Thursday, January 23,  2014

3. Thursday, June 26, 2014

4. Thursday, August 7, 2014

5. Thursday, December 18, 2014

During the January 23,  2014  Citizens Advisory Committee meeting,  three cross-sectional design alternatives for the Hyperion Avenue Bridge were presented to the committee. These cross-sectional design Exhibits, which are posted below, are strictly preliminary design alternatives under consideration,  and do not represent the final design of the bridge.

Cross-Sectional Design Exhibits

 

Also, a General Project Improvement Exhibit is posted for  reference.

General Project Improvement Exhibit

 

 

During the June 26, 2014 Citizens Advisory Committee Meeting, Psomas, a consultant for BOE, presented the results of six technical studies in connection with the Glendale Hyperion Viaduct Complex Improvement Project  in regards to the following:

A. Existing and Future Traffic Demand

B. Assessment of Posted, Operational , and Design Speeds

C. Median Treatment Need Assessment and Countermeasures

D. Operational Assessment

E. Pedestrian Crosswalk Alternatives and Treatments

F. Cross-Sectional Alternatives

The Powerpoint Presentation, the results of these six studies presented as Technical Memoranda, as well as a video of traffic simulations involving different operational analyses alternatives  are posted below

Powerpoint Presentation

 

Technical Memoranda

The link to the  traffic simulations video:

 

During the December 18,  2014  Citizens Advisory Committee meeting, an additional cross-sectional design alternative for the Hyperion Avenue Bridge was presented to the committee. This cross-sectional design Exhibit, which is posted below, is strictly a preliminary design alternative under consideration,  and does not represent the final design of the bridge

Cross-Sectional Design Exhibit 1A

Public Hearing Monday, October 28, 2013 6:00PM

Updates

The City of Los Angeles will hold a public hearing on this project.

When:
Monday, October 28, 2013
6:00PM

Where:
Friendship Auditorium
3201 Riverside Drive
Los Angeles 90027

To learn more about the public hearing please refer to the PDF linked below.

Public Hearing PDF

 

Additional Documents

Glendale Boulevard-Hyperion Avenue Complex of Bridges Improvement Project
(Initial Study with Proposed Mitigated Negative Declaration/Environmental Assessment and Programmatic Section 4(f) Evaluation)

Presentation